Insurance Coverage for Sardar Sarovar Power Project (SSP).
|
|
|
|
|
>
|
Payment of Share cost of Sardar Sarovar Project by the
party States.
|
|
|
|
|
>
|
Draft proposal for Annual Development Plan (2008-2009)
of Unit-I (Dam and Appurtenant) works and Unit-III (Hydro Power)
works of SSP.
|
|
|
|
|
>
|
Revised Implementation Schedule (RIS-September 2003)
for construction of Garudeshwar weir
of SSP.
|
|
|
|
|
>
|
Claim put forth by M/s Jaiprakash
Associates on account of shortfall in concrete progress during
the various working seasons from 1993-94 to 1997-98 due to the
restrictions imposed in raising the spillway of Sardar Sarovar
Dam.
|
|
|
|
|
>
|
Review
of progress of Unit-I and Unit -III works of SSP.
|
|
>
|
Real Time Data Acquisition System (RTDAS) commissioning
of Water Management System.
|
|
>
|
Pending payment to M/s BHEL for their supply of CHPH
& RBPH Hydro equipment.
|
|
>
|
Installation of regulatory mechanism for Godbole gate.
|
|
>
|
Closure
of contract with m/s BHEL for
Work Package- I & II of EMC project.
|
|
>
|
Share cost of SSCAC secretariat.
|