The estimated cost of the Sardar Sarovar Project as approved by the
Planning Commission is Rs.6406.04 crore at 1986-87 price level. Revised Estimated Cost of the project at 2008-09 price
level is Rs 39240.44 crore. An expenditure
of Rs. 32296.10 crore has been incurred on the project up to the end
of September 2010. The expenditure booked under Unit-I (Dam & Appurtenant
works) is Rs. 4596.22 crore, excluding the Group-V (Common expenditure)
component. The expenditure booked under Unit-III (Hydropower works)
is Rs. 2504.04 Crore, excluding Group-V component. Similarly, excluding
Group-V the expenditure booked under Unit-II (Main Canal works) and
Group-IV (works of Branches & Distribution system) are Rs. 5398.98
crore and Rs. 8085.42 crore respectively. Certain expenditures common
to all work components - including the interest component of market
borrowings - have been booked under Group-V (Common Expenditures) and
it amounts to Rs. 12569.92 Crore. Other expenditures incurred by Government
of Gujarat - which are not shareable - are booked under Group-VI (Non
Shareable Expenditure) amounting to Rs. (- 858.48) crore.
The Expenditure Statement showing the expenditure under different units/groups
of the project is given below:
|
Unit/Group
|
Estimated Cost 1986-87 price level/
2008-09 price level
|
Cumulative Expenditure up to September
2010^
|
|
Unit-I (Dam & Appurtenant works)
|
1019.45/ 8930.53
|
4596.22
|
|
Unit-II
(Main Canal)
|
1588.54/
23864.03
|
5398.98
|
|
Unit-III (Hydro Power)
|
979.95/
2910.88
|
2504.04
|
|
Group-IV (Branches & Distributory Network)
|
2818.10/
3535.00
|
8085.42
|
|
Group-V (Common Exp.)
|
|
12569.92
|
|
Group-VI (Non-Shareable Exp.)
|
|
-858.48
|
|
Total……..
|
6406.04/
39240.44
|
32296.1
|
^ As per information given by SSNNL
|