CANAL HEAD POWERHOUSE
The CHPH is a surface power station in a Saddle Dam on the right bank
at the fringe of the first balancing storage pond with installed capacity
of 250 MW (5 units of 50 MW each), deploying Kaplan turbines. The Civil
and Electrical works of Canal Head Power House were completed in all
respect in January 1998; however, power could only be generated after
the dam had attained the height of EL 110.64 m. All the five units of
CHPH (1x50 MW) have been commissioned successfully during August 2004
to December 2004.
RIVER BED POWERHOUSE
The River Bed Power House (RBPH) is an underground power
station on the right bank of river located about 165 m downstream of
the Dam. The underground RBPH has 6 units of 200 MW each, deploying
Francis type reversible turbines. The civil works of the RBPH commenced
in July 1987. The civil works of RBPH were scheduled for completion
by 1995 but due to development of distress zone in walls of the power
house cavern, further excavation was stopped and the affected zones
were treated. The civil works of RBPH was also suspended for some time,
due to delay in supply of embedded parts of Turbine-Generator (TG) sets.
However the issue of the procurement of TG sets was settled with M/s.
Sumitomo Corporation (Japan), and with the commencement
of supply of equipment, the balance excavation work in the powerhouse
cavern started in June 1999. As per Revised Implementation Schedule
(RIS) of June 2002 approved by the SSCAC in its 69th meeting held on
29th July 2003, the milestone dates for various activities were fixed
as per Table given below:
The civil & electrical works
of River Bed Power House have been completed for all six units. All
six Units of RBPH were commissioned on 01.02.2005, 30.04.2005, 30.08.2005,
28.10.2005, 07.03.2006 and 20.06.2006 respectively. The status of progress
of civil works of RBPH at the end of March 2010 is given in Table.
|
Table
PROGRESS OF CIVIL WORKS OF RBPH UPTO JUNE 2010
|
|
S.No
|
RBPH
Civil Works
|
Unit
|
Total Revised Estimated
Quantity
|
Work done up to
June 2010
|
Percentage of Completion
|
|
|
Open
Excavation
|
TCM
|
1715.00
|
1703.36
|
99.32
|
|
|
Underground
Excavation
|
TCM
|
732.06
|
688.07
|
93.99
|
|
|
Concreting
|
TCM
|
335.19
|
311.88
|
93.05
|
|
|
Shotcreting
|
TCM
|
207.73
|
184.86
|
88.99
|
|
|
Rock
bolting
|
TRM
|
168.18
|
142.01
|
84.44
|
Note: TCM: Thousand Cubic Metre TSM: Thousand
Square Metre TRM: Thousand Running Meter
The work
of Lighting in RBPH Power House, Lift and Fire Fighting system, Air
Conditioning, Ventilation system and provision of Computerized Control
System (C.C.S) of RBPH have also been completed.
|