> HYDROPOWER COMPLEX:
CANAL HEAD POWERHOUSE

The CHPH is a surface power station in a Saddle Dam on the right bank at the fringe of the first balancing storage pond with installed capacity of 250 MW (5 units of 50 MW each), deploying Kaplan turbines. The Civil and Electrical works of Canal Head Power House were completed in all respect in January 1998; however, power could only be generated after the dam had attained the height of EL 110.64 m. All the five units of CHPH (1x50 MW) have been commissioned successfully during August 2004 to December 2004.


RIVER BED POWERHOUSE

The River Bed Power House (RBPH) is an underground power station on the right bank of river located about 165 m downstream of the Dam. The underground RBPH has 6 units of 200 MW each, deploying Francis type reversible turbines. The civil works of the RBPH commenced in July 1987. The civil works of RBPH were scheduled for completion by 1995 but due to development of distress zone in walls of the power house cavern, further excavation was stopped and the affected zones were treated. The civil works of RBPH was also suspended for some time, due to delay in supply of embedded parts of Turbine-Generator (TG) sets. However the issue of the procurement of TG sets was settled with M/s. Sumitomo Corporation (Japan), and with the commencement of supply of equipment, the balance excavation work in the powerhouse cavern started in June 1999. As per Revised Implementation Schedule (RIS) of June 2002 approved by the SSCAC in its 69th meeting held on 29th July 2003, the milestone dates for various activities were fixed as per Table given below:

Table

MILESTONE DATES FOR RBPH (RIS-JUNE 2002)


S. No.
Name of Activity
Target date for completion
1
Civil Works of powerhouse cavern      30.06.2005
2
Construction of Tail Race Channel      31.05.2004
3
Fabrication and erection of Penstocks      31.12.2004
4
Supply & erection of draft tube gates in Collection Pool and trash rack in exit tunnels.      31.12.2001
5

Commissioning of RBPH

Unit I
Unit-II
Unit-III
Unit-IV
Unit-V
Unit-VI

 




     31.09.2004
     31.01.2005
     31.05.2005
     30.09.2005
     31.01.2006
     31.05.2006 (Sixth/Final      Unit)











The civil & electrical works of River Bed Power House have been completed for all six units. All six Units of RBPH were commissioned on 01.02.2005, 30.04.2005, 30.08.2005, 28.10.2005, 07.03.2006 and 20.06.2006 respectively. The status of progress of civil works of RBPH at the end of March 2007 is given in Table.


Table

PROGRESS OF CIVIL WORKS OF RBPH UPTO MARCH 2007

S.No

RBPH
Civil Works

Unit

Total Revised Estimated
Quantity

Work done up to March 2007

Percentage of Completion

  Open Excavation
TCM
1715.00
1703.36
99.32
Underground Excavation
TCM
732.06
688.07
93.99
Concreting
TCM
335.19
311.88
93.05
Shotcreting
TCM
207.73
184.86
88.99
Rock bolting
TCM
168.18
142.01
84.44

Note: TCM: Thousand Cubic Metre TSM: Thousand Square Metre TRM: Thousand Running Meter

The work of Lighting in RBPH Power House, Lift and Fire Fighting system of RBPH have already been completed. The work of Air Conditioning, Ventilation system and provision of Computerized Control System (C.C.S) of RBPH are in progress.


SWITCH YARDS

The work of erection of 220 KV Switchyard structure for the Canal Head Powerhouse is completed in all respect. Building for the main 400 KV switchyard has also been completed. Contract for procurement of 400 KV Gas Insulated Switchgear (GIS) equipment was signed with M/S GEC Alsthom (France) in August 1992. Erection of all GIS (Gas Insulated Switchgear) bays and GIB (Gas Insulated Busbar) bays is completed including its wiring, gas filling, pre-commissioning H.V. testing and die-electric testing. Final commissioning shall be done along with commissioning of Turbine Generator Sets.

TRANSMISSION LINES

For transmission of the power generated by two power houses of Sardar Sarovar Project six transmission lines have been constructed. The works of SSP- Maharashtra (Dule) borderline, SSP- Madhya Pradesh (Nagda) boarder line and SSP- Kasor & Asoj (Gujarat) have been carried out by Gujarat Electricity Board (GEB).

The State wise charging of Transmission Lines is given as below:

State

Transmission Lines

Charging Date

Gujarat SSP-Kasor Lines
SSP-Asoj Lines
charged on 07.12.2004
charged on 07.12.2004
Maharashtra SSP-Dhule-I Lines
SSP-Dhule-II Lines
charged on 07.12.2004
charged on 24.03.2006
Madhya Pradesh SSP-Nagda-I Lines SSP-Nagda-II Lines charged on 07.12.2004 charged on 30.09.2006