|
|
|
|
|
Monitoring
|
|
|
|
|
|
|
|
|
|
>
HYDROPOWER
COMPLEX:
|
![]() |
CANAL HEAD POWERHOUSE The CHPH is a surface power station in a Saddle Dam on the right bank at the fringe of the first balancing storage pond with installed capacity of 250 MW (5 units of 50 MW each), deploying Kaplan turbines. The Civil and Electrical works of Canal Head Power House were completed in all respect in January 1998; however, power could only be generated after the dam had attained the height of EL 110.64 m. All the five units of CHPH (1x50 MW) have been commissioned successfully during August 2004 to December 2004. RIVER BED POWERHOUSE The River Bed Power House (RBPH) is an underground power station on the right bank of river located about 165 m downstream of the Dam. The underground RBPH has 6 units of 200 MW each, deploying Francis type reversible turbines. The civil works of the RBPH commenced in July 1987. The civil works of RBPH were scheduled for completion by 1995 but due to development of distress zone in walls of the power house cavern, further excavation was stopped and the affected zones were treated. The civil works of RBPH was also suspended for some time, due to delay in supply of embedded parts of Turbine-Generator (TG) sets. However the issue of the procurement of TG sets was settled with M/s. Sumitomo Corporation (Japan), and with the commencement of supply of equipment, the balance excavation work in the powerhouse cavern started in June 1999. As per Revised Implementation Schedule (RIS) of June 2002 approved by the SSCAC in its 69th meeting held on 29th July 2003, the milestone dates for various activities were fixed as per Table given below:
|
||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||
|
The civil & electrical works of River Bed Power House have been completed for all six units. All six Units of RBPH were commissioned on 01.02.2005, 30.04.2005, 30.08.2005, 28.10.2005, 07.03.2006 and 20.06.2006 respectively. The status of progress of civil works of RBPH at the end of March 2007 is given in Table.
Note: TCM: Thousand Cubic Metre TSM: Thousand Square Metre TRM: Thousand Running Meter The work of Lighting in RBPH Power House, Lift and Fire Fighting system of RBPH have already been completed. The work of Air Conditioning, Ventilation system and provision of Computerized Control System (C.C.S) of RBPH are in progress. |
|
|
|||||||||||||||||||||